Orbit Centre Car Park

New car parking for office block.

  • £0k+

    Project Value

Client: Merthyr Tydfil Council.

Dates: 2017.

Project Work Types: Earthworks, Drainage, Footpaths, Kerbing, Roads construction, Ducting.

Project Delivery: In house resources, Final surfacing subcontract.

Project Specialities: Material Management – cut & fill on earthworks, recycled aggregates.

Environmental: Working close to trees, site boundary acts as tree protection zone.

Value Engineering: Minimal muck away.

Client Feedback: Neat looking job, very good workmanship on the kerbing.

M4 Junction 28

Improvements to junction 28 of the M4.

  • £0k+

    Project Value

Client: Welsh Government / Costain / McCarthy.

Dates: Sept 2017 to Nov 2018.

Project Work Types: Earthworks, Drainage, Footpaths, Paving, Kerbing, Ducting, Finishes.

Project Delivery: In house resources.

Project Specialities: Working with live traffic and a phased construction.

Environmental:Dust and silt management.

Value Engineering: Managing the programme to ensure each phase was completed in a timely manner.

Client Feedback: “I am delighted to mark the completion of this £13.7million construction project that will not only boost traffic flow but also improve road safety in the area.” Ken Skates – Minister for Economy and Transport.

Duke St - Pontypridd

Drainage improvement works within the Highway.

  • £0k+

    Project Value

Client:Rhonda Cynon Taff Council / Horan.

Dates: Dec 2019 to Jan 2020.

Project Work Types: Drainage, Highway Reinstatement, Traffic Management.

Project Delivery: In house resources, Final surfacing subcontract.

Project Specialities: Working with live traffic and a phased construction.

Environmental:Dust and silt management.

Value Engineering: Recycling the tarmac and old subbase for reuse.

Client Feedback: Pleased with the outcome and the professionalism of the team.

The Rise Highway

Secant pile wall and capping beam to support the highway masonry wall.

  • £0k+

    Project Value

Client: Intelle Construction.

Dates: Start June 2020 – ongoing.

Project Work Types: Pile cropping, RC works, retaining walls, Earthworks.

Project Delivery: In house resources, Piling subcontract.

Project Specialities: Small site with minimal operating space.

Environmental: Managing noise levels for the local community.

Value Engineering: All works completed from the rear of the wall to minimise disturbance to the highway A4119.

Client Feedback: Greatly assisted the Site Manger with forward thinking and planning, the weekly programmes helped complete the first phase early.